Continuing on with framing in between rain storms.  Should be completely framed in this week, weather permitting.

Kitchen beam has been installed and all floor joists cut back and reattached.

Explained the door from garage to Dave.  We will remove the old garage door and frame in a new one with stairs to the new garage slab.

Could everyone please step up their cleaning after the working day and be as conscientious as we usually are.  Please be sensitive to all construction related messes i.e. dust, foot traffic even if it doesn't belong to you.  If you see it you are responsible for it even if it comes from another sub.  If you are having to clean up after other subs too much please bring it to my attention.  Last week got a little lax while I was away.

Gas meter will be located on the left front corner of the house because it cant be installed under the porch.