- Plaster is complete.
- Exterior stairs complete.
- Start Trimming the doors and windows - 9/12 - 9/14
- Install interior doors - 9/12 - 9/14
- Tile Master Bath floor & walls, and 1st floor fireplace- 9/12-9/14
- Run gas line in basement.
- Install garage door. 9/12 - 9/14
- Meet with Landscaper - 9/14
This blog is a way for us to keep track of everything that we talk about, suggest or do at your home over the life of our working relationship. It is updated, usually, on a daily basis during the project. Here we will record daily activity on the job, list recommendations on products and materials and add articles that pertain to your home.