- We will install 2 posts and a header at catwalk. The posts to line up with the stair stringers and same distance off opposite wall.
- Dave will share cost of gutters and downspout install.
- Extra kitchen work for electrical and plumbing due to issues uncovered during construction, will be invoiced after costs are accumulated.
- Still need to discuss actual driveway layout.
This blog is a way for us to keep track of everything that we talk about, suggest or do at your home over the life of our working relationship. It is updated, usually, on a daily basis during the project. Here we will record daily activity on the job, list recommendations on products and materials and add articles that pertain to your home.
Click on Images to enlarge
Friday, August 17, 2012
Meeting Notes - 8/17/12
Dave Malin, Laura Lee, Peter Stames, Mike Norton